On Monday, February 17, 2025, SPS Technologies experienced a major fire that broke out at our fastener manufacturing operation in Abington Township. Thankfully, our team members working at the time of the fire are safe and well.

We are providing the information and resources on this site to keep our community up to date on what’s happening. If you have questions or concerns, please contact us.

Jenkintown

Aug. 14, 2025

Update: Highland Ave. To Intermittently Close beginning Aug. 18th

Highland Avenue will be intermittently closed during the week of August 18th, rather than the originally planned two-week full closure. During this time, the demolition contractor will safely remove the buildings and structures along the street. SPS’s contractor will work to complete the project as efficiently as possible to minimize disruptions.

Read more

Jul. 30, 2025

Highland Ave. To Close on Aug. 18th

Highland Avenue will be closed from August 18th to August 29th to safely remove the buildings/structures along the street. SPS’s contractor will endeavor to complete the work as quickly as possible, and the street will be reopened as soon as safely possible. Highland Avenue will be closed from August 18th to August 29th to safely remove the buildings/structures along the street. SPS’s contractor will endeavor to complete the work as quickly as possible, and the street will be reopened as soon as…

Read more

Jul. 29, 2025

Demolition Process on Schedule

SPS continues its demolition efforts, which are on schedule. An overview of the demolition and air monitoring plans can be found here.

Read more

May. 19, 2025 - July 27, 2025

Community and Residential Testing Results Posted

Based on testing performed by TRC, an environmental testing company, at community and residential sites, there is no discernible impact from the SPS Technologies fire.  Please visit the Testing Results section to learn more and view the complete report.

Read more

May. 13, 2025 - May 18, 2025

SPS to Begin Demolition Phase

On or after May 19th, SPS will begin the Demolition phase.  An overview of the demolition and air monitoring plans can be found here.  If you have questions or concerns, please use the contact section.

Read more

May. 09, 2025 - May 12, 2025

SPS will Transition from Reclamation to Demolition Phase

SPS is concluding its Reclamation phase, in which products (finished, in-process, and raw materials) and equipment were removed.  On or after May 19th, SPS will begin the Demolition phase, and an overview of the demolition and air monitoring plans will be posted on the website soon.  If you have questions or concerns, please use the contact section to reach out.

Read more

May. 02, 2025 - May 08, 2025

Additional Air and Water Monitoring Reports Posted

SPS has posted additional air and water monitoring reports to the Monitoring section. If you have debris in your yard or would like to be added to the list for roof and gutter inspection/cleaning, please submit a request with your contact information and address through the Contact section.

Read more

Apr. 28, 2025 - May 01, 2025

Roof and Gutter Inspection/Cleaning Offered

If you have debris in your yard or would like to be added to the list for roof and gutter inspection/cleaning, please submit a request with your contact information and address through the Contact section.

Read more

Apr. 26, 2025 - Apr. 27, 2025

Highland Avenue to Reopen on April 28th at Approx. 8 am

On Monday, April 28, 2025, at approximately 8:00 am, Highland Avenue will reopen to traffic between Mt Carmel Ave. and Wharton Rd. Moving forward, from 7:00 a.m. to 7:00 p.m., SPS Technologies will employ flaggers when necessary to allow movement of materials across Highland Avenue.

Read more

Apr. 25, 2025

Additional Water Monitoring Reports Posted

SPS has posted additional water monitoring reports to the Monitoring section. On Monday, April 28, 2025, at approximately 8:00 am, Highland Avenue will reopen to traffic between Mt Carmel Ave. and Wharton Rd.  Moving forward, from 7:00 a.m. to 7:00 p.m., SPS Technologies will employ flaggers when necessary to allow movement of materials across Highland Avenue.

Read more